Home construction cost estimator
Quick estimate of turn-key construction cost from area, house type, foundation, roof and material tier — reference market rates.
Enter the land area and pick house type, foundation, roof and material tier to estimate turn-key construction cost.
Enter the area then click “Estimate cost” to see the result.
Source & verificationUtility tool
A convenience tool — the computation is mechanical on your inputs and is not based on any design standard.
Cost area from conversion factors (foundation/slab/roof) times turnkey unit rates — Vietnamese market references ~2025–2026, not applicable norms. For preliminary estimates only.
About the home construction cost estimator
A quick estimate of turn-key home construction cost for homeowners — answers “how much does a 100 m² house cost to build” before commissioning a detailed estimate.
What you enter
Buildable land area — ground-floor footprint (m²), house type (single-storey, 1–3 storey townhouse, villa), foundation type (single, strip, pile, raft), roof type (metal sheet, flat concrete, tile-on-steel, tile-on-concrete) and material tier (basic, standard, premium).
What the result means
Estimated total cost (₫) with a breakdown: adjusted areas of the foundation, floors and roof; total charged area and the applied turn-key unit rate — a reference figure for budgeting.
Use cases
Budget before building a single-storey home, townhouse or villa; compare foundation/roof options and material tiers; sanity-check turn-key contractor quotes; answer “what does a 100 m² house roughly cost”.
Unit rates and adjustment factors are common Vietnamese market reference values — not official norms or binding prices. Actual cost varies with location, material and labour prices, soil conditions, detailed design and each contractor's scope — not a substitute for a drawing-based estimate or a construction contract.
Worked example
A 2-storey townhouse on an 80 m² footprint with strip footing (44 m²), floors (160 m²) and tile-on-steel roof (56 m²) → charged area ≈ 260 m²; standard tier ≈ 5.7 million ₫/m² → estimated cost ≈ 1.48 billion ₫.
Frequently asked questions
How much does a 100 m² house cost to build?
Reference: a 2-storey townhouse on a 100 m² footprint with strip footing and tile roof at the standard tier ≈ 1.85 billion ₫ (charged area = 200 + 55 + 70 = 325 m² × 5.7 million ₫). Enter your own specs for a tailored figure.
Where do the turn-key rates per m² come from?
Rates commonly quoted by Vietnamese contractors: single-storey ≈ 5.3 million ₫/m², townhouse ≈ 5.5–5.9 million ₫/m², villa ≈ 7.2 million ₫/m² at the standard tier — market reference figures, not quotes.
What do the foundation/roof factors mean?
The area-adjustment convention used in turn-key quotes: foundations and roofs are not charged at full floor area but multiplied by a factor (strip footing ≈ 55%, metal-sheet roof ≈ 30%…) then added to the floor area before applying the unit rate.
Can this estimate replace a detailed cost estimate?
No — this is a quick estimate for budgeting. An accurate figure needs quantity takeoff from drawings and local rates — sign up for BuildLab to get a detailed estimate from DWG drawings.
Related articles
- Bóc khối lượng móng công trình: móng đơn, móng băng, móng cọc và đà kiềng
Phần móng là nhóm công tác đầu tiên và cũng dễ sai sót nhất khi bóc tách khối lượng: nhiều công tác "ẩn" (đào đất, bê tông lót, đắp trả) không nhìn thấy trên mặt bằng kết cấu, và q…
- Bóc khối lượng cột, dầm, sàn bê tông cốt thép: công thức và quy tắc trừ lùi
Khung bê tông cốt thép — cột, dầm, sàn — chiếm tỷ trọng lớn nhất trong khối lượng kết cấu của nhà ở và chung cư. Ba công tác luôn đi cùng nhau (bê tông, ván khuôn, cốt thép) và cùn…
- Bóc khối lượng xây trát và hoàn thiện: quy tắc trừ cửa, ốp lát, sơn bả
Phần hoàn thiện — xây tường, trát, ốp lát, sơn bả — có đặc điểm khối lượng lớn, mã hiệu nhiều và phụ thuộc mạnh vào bản vẽ kiến trúc (kích thước cửa, cao độ, chủng loại vật liệu).…
How it works
The tool estimates turn-key construction cost using the “adjusted construction area” method common in Vietnamese contractor quotes: charged area = foundation (factor × ground-floor area) + floors (ground-floor area × storeys) + roof (factor × ground-floor area); estimated cost = charged area × turn-key unit rate/m².
Common reference factors: single footing ~30–40%, strip footing ~50–70%, pile ~30–50%, raft ~80–100%; metal-sheet roof ~20–30%, flat concrete ~40–50%, tile-on-steel ~60–70%, tile-on-concrete ~80–100%. Reference turn-key rates (shell + finishes): single-storey ~4.8–5.9 million ₫/m², townhouse ~5.0–6.6 million ₫/m², villa ~6.5–8.2 million ₫/m² by material tier.
Results are indicative budget estimates only — actual cost varies with location, material and labour prices, soil conditions, detailed design and the contractor's scope; not a substitute for a drawing-based estimate.